New Road Construction UPDATE

HAPPY HOLIDAYS

Due to anticipated unfavorable weather, no work will be done Thursday or Friday.  On Monday 12/22 the balance of Parchester, part of Ellington, Atherstone and Holborn Ct. will be paved, and St. Andrew and Henderson will be milled out, and paved Tuesday 12/23.  Speed humps for any roads will probably not be installed until 1/6/2026 due to the asphalt plants being closed for the Holidays.

UPDATE:

As of 12/17 at 2:00 PM Dartmoor, Sanborn, Blandford and part of Parchester, there has been a production issue at the asphalt plant that will result the work scheduled for today not being completed as anticipated.  Going forward all schedules are tentative.  Review this site daily for any changes. Happy Holidays to all!!